18/01/2017
I put a structure document together for the proposal.
Supervisors were allocated today. My Supervisor is Elizabeth
Bourke.
19/01/2017
Today I met with the FYP Project Coordinator. I worked on
points and guidance from the meeting.
From the Project Management class, we covered Gantt Charts
in Microsoft Excel. I drew up this chart and then did some online research of
different Gantt Chart layouts and styles. Decided on chart with functionality
that each timeline date bar also has a progress bar to update as the project
proceeds. It includes start date, end date, duration and progress bars.
Figure 1: Gantt Chart
On my proposal document there is a link to a larger screen versionof the Gantt Chart. (not working in blogger). Also, I'll draw up one
with less detail to fit the blog page.
20/01/2017-22/01/2017
Completed proposal.
From Project Management I created a layout of the project
parts.
Figure 2: Layout of potential project parts